The Heights Munduk has been under construction since July 2025, it is around 65% complete, and it is on track for handover in December 2027. This page is an open, ongoing log of where the build stands, with recent drone footage you can watch today.
Where the build stands today
The heavy, capital-intensive phase is complete. What stands on site today is a resort well into its finishing stages: the structural work is done and the detailed finishing is underway.
- Land & platform: the full 1.2-hectare site is secured and levelled, the slopes engineered and retained.
- The suspended road: Bali's first canopy-level access road is formed, threading the hillside to every villa.
- Structures: the full concrete structures are up on seven of the eight villas, plus the lobby and restaurant pavilion.
- Now underway: architectural finishing, facades, joinery and interiors, has begun.
- The eighth villa: the four-bedroom Signature is offered off-plan and delivered with the estate by handover.
Under construction since July 2025, around 65% complete, and on track for December 2027 — progress you can verify for yourself.
See the site for yourself
Nothing shows the progress more clearly than the footage itself. These are recent flights over the site: the hillside, the structures and the suspended canopy road.
More films will follow here as the build advances.
Who is building it
The Heights Munduk is built by HMK, the contractor behind the Apurva Kempinski Bali, the island's benchmark for five-star craft. The villas are designed by the studio behind Alila Villas, and the project is developed by Conceptive, the team that already delivered The Heights Melasti and The Heights Bingin, both sold out. Construction is fully contracted with HMK, and payments are released in stages against completed, independently verified milestones.
The road to handover
- Done: site works, retaining, suspended road, structures on seven villas and the pavilion.
- In progress: architectural finishing, facades and interiors.
- Next: MEP (mechanical, electrical, plumbing) and fit-out.
- Final months: furniture and FF&E, then landscaping.
- Handover: December 2027.
Full documentation, on request
Serious investors are welcome to examine the full record behind the project: construction contracts and invoices, the staged payment schedule, land title and lease documentation, and the complete corporate structure. Every layer of this development is documented and independently verifiable, and the full file is made available to qualified parties conducting due diligence.
A built asset, before the airport.
Around 65% complete, offered at construction cost, one hour from North Bali's new international airport. Whole resort or villa by villa. Handover December 2027.
Figures and timelines are indicative and subject to change. Renders are for illustration only. This is a marketing update, not an offer, solicitation, or investment advice.